Key points
- Under PP 16/2021, a PBG covers building new, altering, extending, reducing and maintaining a building.
- The structural part of a PBG includes calculations, design drawings, detail drawings and specifications.
- Buildings above two storeys need a soil investigation in the application.
- Technical documents are prepared by certified providers and assessed through consultation with the TPA.
Before a building can be built in Indonesia, its owner needs a Building Approval (Persetujuan Bangunan Gedung, PBG). One of the heaviest parts of a PBG application is the structural package: calculations, design drawings and specifications. This article explains how building approval (PBG) relates to structural design, which documents are usually requested, and what a structural engineer does to keep the process moving.
What is a building approval (PBG)?
Government Regulation (PP) 16/2021 defines PBG as the approval given to a building owner to construct, alter, extend, reduce and/or maintain a building in line with the building technical standards (Article 1 point 17). PBG replaced the former building permit (IMB) under PP 36/2005, the regulation that PP 16/2021 replaced.
Two points matter here:
- PBG is not only for new buildings. Alterations, extensions and reductions are covered too. Article 11(2) of PP 16/2021 requires the owner to apply for an amended PBG when a building's function and/or classification changes.
- The test is compliance with technical standards, not just complete paperwork, so the technical documents, including structure, sit at the heart of the review.
Applications go through the Building Management Information System (SIMBG). According to a 2026 briefing by the Directorate General of Human Settlements, SIMBG is now integrated with OSS, so businesses apply for PBG and SLF through OSS.
Structural documents for a PBG
The official briefing on building regulation under PP 16/2021 and PP 28/2025 splits PBG technical data into architecture, structure, and mechanical, electrical and plumbing (MEP). For structure it lists:
- Technical calculations and design drawings of foundations, basements, columns, beams, floor slabs, roof framing, cladding and other building components.
- Structural detail drawings.
- Technical specifications.
Land data is also required: proof of ownership and technical land data, including contours and information from the soil investigation. Applicants for buildings up to two storeys are not required to attach a soil investigation, which means that for anything taller, the geotechnical data should be prepared early.
| Document | What is usually reviewed |
|---|---|
| Structural calculation report | Loads, seismic analysis, member design, foundations |
| Structural design drawings | Foundation plan, floor plans, sections |
| Detail drawings | Connections, typical reinforcement, special details |
| Technical specification | Concrete grade, steel grade, reference standards |
| Soil investigation report | Soil layers, foundation design parameters |
Exact content and formats can differ between local governments, so check the requirements of the city or regency concerned.
Who prepares and who reviews
The same briefing states that technical data must be prepared by a certified construction services provider. For structure, that means calculations and drawings by a qualified structural engineer, not copied from another project.
The review is carried out by the local government. PP 16/2021 describes the Expert Professional Team (TPA) as a team of professionals appointed by the city or regency government to give technical advice on building matters. The design documents are assessed through a consultation process, using a checklist that covers architecture, structure and MEP.
Tip: When the TPA comments on the structure, it is usually about load assumptions, seismic parameters or soil data. Ask your engineer to attend or to prepare written responses so revisions do not go back and forth.
The structural engineer's role in the PBG process
A structural consultant does more than run numbers. For a PBG the role covers:
- Setting the design basis: reference standards (such as SNI 1726:2019 for seismic design and SNI 2847:2019 for structural concrete), material grades and design loads.
- Coordinating soil data: deciding what investigation is needed and turning the results into foundation design through geotechnical engineering.
- Preparing consistent reports and drawings: the values in the calculation report must match those on the drawings. Our guide to structural drawings explains how to read them.
- Responding to TPA comments and revising the documents when asked.
- Supporting the SLF stage: as-built drawings and a functionality inspection are needed before the building is occupied.
Common causes of delay
Structural packages are often returned because:
- There is no soil investigation, or it does not represent the site, for a building above two storeys.
- The architectural drawings changed (an added storey, moved columns, new openings) but the structural calculations were not updated.
- The calculation report does not state its reference standards or seismic parameters.
- Details are missing, such as connections or stair details.
- The designer cannot show the relevant competency certificate.
Most of these can be avoided by coordinating architecture and structure from the start, and by appointing the right designer; see how to choose a structural engineer.
Existing buildings
PBG also matters for existing buildings. Adding a storey, changing the use (say, from house to office) or extending the building means the structure must be re-checked for the new conditions. For buildings already in use, the functionality inspection for an SLF often needs an assessment of the existing structure, especially when the original drawings are incomplete. Government projects such as the BNPT Office and others in our government buildings sector go through similar approval and technical review steps.
Conclusion
A PBG is essentially proof that a building design meets the technical standards, and structure is the most heavily reviewed part. Commission the soil investigation early, keep calculations and drawings consistent, and involve a competent engineer so the TPA consultation runs efficiently. Every building needs its own calculations by a qualified engineer. Stadin can prepare the structural design for your PBG and the supporting documents for the SLF.
This article provides general information. Every project still needs to be analysed and calculated by a competent structural or geotechnical engineer, in line with the applicable SNI codes and regulations.
Sources
- Penyelenggaraan Bangunan Gedung sesuai PP 16/2021 & PP 28/2025 (bahan sosialisasi Ditjen Cipta Karya, Universitas Padjadjaran, 2026)
- Peraturan Pemerintah Nomor 16 Tahun 2021 tentang Peraturan Pelaksanaan UU Bangunan Gedung (JDIH Kementerian PKP)
- Paradigma Baru Mendirikan Bangunan – Hukumonline
- Data proyek: company profile PT. Stadin Strukturindo Konsultan (2026)